Project Progress

Spectrum pile load testing works as on 8th August 2018

Spectrum work progress as on 6th August 2018

Spectrum Piling Works Completed on 31st July 2018

Work Progress as on 7th July 2018

Work Progress as on 23rd June 2018

Piling Started on 19th June 2018

Varma Spectrum Bhoomi Pooja and Stone Laying Ceremony was held 30th April 2018